Byrnes Road, MP 1.80 to MP 1.90
Repair bank that was damaged during high water events.
Vicinity Map
CRP Number:
17-06
Funding Source:
FEMA
Project Cost:
$210,000
Construction Date:
July 2024
Completion Date:
October 2024
Update:
Currently working on project design.
Project Documents:
Contact Information:
Seth Walker, PE
Chief of Engineering and Construction
(509) 524-2710
Email