The existing bridge is load restricted and posted for loads because of the bridge deck. This project will rehabilitate the existing bridge deck, bridge railing, and guardrail.
CRP Number:
20-03
Funding Source:
STP(BR) and County
Project Cost:
$1,081,250
Construction Date:
May 2021
Completion Date:
July 2021
Update:
The construction contract has been awarded to N.A. Degerstrom Inc., from Spokane, WA. The first working day of the contract is May 17, 2021. The last working day of the contract will be July 20, 2021. During construction Sudbury Road will be closed from Dry Creek Road and Loney Road. A detour is in place. Please contact Walla Walla County at 509-524-2710 if you have any questions.
Por favor llame a este número 509-524-2710 si necesita más información o para recibir esta información en español.
Project Documents:
Contact Information:
Seth Walker, PE
Chief of Engineering and Construction
(509) 524-2710